Big Hill Road had suffered a landslide during the heavy rains of 2021. Site investigations and a detailed design for a retaining structure had been completed. Council was in the process of seeking Disaster Relief funding when the 2022 rain events occurred.
The site suffered reactivation during the 2022 rain events. The retaining structure design has been amended and the procurement of a construction contractor has been complete.
The road will be closed until the retaining structure has been completed. Please allowed additional travel time as an alternate route is required.
Key Details
Suburb | The Oaks |
---|---|
Category | Road, |
Status | Complete |
Start Date | Tuesday, 14 June 2022 |
End Date | Friday, 1 September 2023 |