The construction of a new two-storey Amenities Building on the Western side of the football field will provide change rooms (total of 4), Multi-purpose Room, Club Room, Referee Change Rooms, Caller Box, Toilet amenities, Equipment Storage and Grandstanding seating for the current user groups including rugby league (Juniors and seniors), cricket, netball and astronomy clubs.
This project is funded through NSW Government's Western Sydney Infrastructure Grants Program.
Milestone | Status | Timeframe |
Project Commencement | Scheduled | January 2024 |
Dudley Chesham Sportsground Multipurpose Building is moving along quickly now with the brick work nearly completed. Wall cladding and waterproofing of wet areas is continuing well.
The Dudley Chesham Sportsground Multipurpose building is progressing very well and really taking shape. The roof sheeting is currently being installed along with the utility fit out indoors.
The brickwork is continuing and concrete blade walls are now fully constructed. Installation of the stormwater lines is continuing.
The Dudley Chesham Sportsground multipurpose building is starting to take with now. See the updates:
You can now see the footprint of the Dudley Chesham Sportsground multipurpose building and it's really good. Here is an update on the work on site.
Here is where we are up to with the Dudley Chesham Sportsground multi-purpose building.
There is lots happening at the Dudley Chesham Sportsground - multipurpose facility before we can start building. The installation of the piers is now complete and other service installation will commence shortly.
Excavation is coming along well at the site with the installation of 132 piers due to be completed soon.