PROJECT BACKGROUND
Wollondilly Shire experienced record rainfall throughout March and April of 2022 during what had already been a wet summer. The heavy rainfall triggered geotechnical instability across the shire which caused significant damage to Council road infrastructure through landslips and rock falls. Council is in the process of repairing road damage sites through assistance of NSW Disaster Assistance funding.
Key Details
Suburb | Picton |
---|---|
Category | Road |
Status | Complete |
Start Date | Wednesday, 30 March 2022 |
End Date | Tuesday, 8 August 2023 |