The Barrallier Park Water Play facility is completed and ready for use when the weather warms up in September or October.
Here is a sneak peak of the official opening and the water play elements in action.
The Barrallier Park Water Play area has now been landscaped. The facility will be operational in September. Watch this space for a community launch.
The small scale water park at Barrallier Park nearly completed. See the progress here:
Here is an update on the Barrallier Park Water Play project. It's really starting to take shape.
Blockwork to the Accessible WC, Change Room and Plant Room completed.
Backfilling behind the retaining and reshaping existing ground completed.
Roof to building commenced.
Shade sail posts have been installed.
Preparation of concrete paths, stairs and ramp have commenced. Concrete to be poured week commencing 8/04/2024.
Existing picnic setting has been reinstalled.
The installation of the Barrallier Park Water Play facility is progressing well. Please see the update:
The splash pad for the Barrallier Park Water Play facility is starting to take shape now. Here is where the project is currently up to:
Temporary fencing is now in place at the Barrallier Park Water Play site and work began this week on the project.