The project
The work on Remembrance Driveway will consist of embankment regrading, drainage improvement, geotechnical stabilisation, and the installation of rock bolts and rock fall mesh. Engineers will investigate the condition of the road, and depending on the outcome this will open the way for the removal of the concrete barriers.
Once the work is completed, it should strengthen the embankment to lessen the likelihood of further damage in the future. It is estimated that the project should take approximately six months to complete.
The project is co-funded by the NSW Disaster Recovery Fund as part of a bulk grant for damage caused effecting roads in the severe weather and flooding of February 2022.
Key Details
Suburb | Picton |
---|---|
Category | Major Project |
Status | Complete |
Start Date | Thursday, 1 February 2024 |
End Date | Friday, 18 October 2024 |