The Project
Wollondilly Shire Council and Picton Rangers Soccer Club have secured funding to upgrade the amenities at Picton Sportsground. The extension will more than double the footprint of the existing building and will comfortably accommodate local teams, visiting clubs and spectators. Work will begin on site in early January 2024 and should be completed and ready for use by the end of 2024.
Upgrades include extensions to the existing building to add home and away change rooms, a club room, a multipurpose room including space for emergency services, improvements to the existing canteen, storage, referees’ rooms, a first aid room, an outdoor barbecue area, spectator seating and connection to town water.
Picton Rangers Soccer Club secured two grants for the project including the 2019 Sports Election Commitment Program with the NSW Office of Sport and the Black Summer Bushfire Recovery Grant through the Commonwealth Government, Department of Industry, Science, Energy and Resources amounting to a total of more than $3.2M.
Key Details
Suburb | Picton |
---|---|
Categories | Major Project, Playgrounds, Parks & Sportsgrounds |
Status | In Progress |
Start Date | January 2024 |
End Date | December 2024 |