The carpark at Tahmoor District Sporting Complex is progressing well with the kerb and guttering in the final stages. Next step is the laying of the asphalt surface.
The redevelopment of the sportsground is now complete including the irrigation, drainage, complete realignment, fencing, guttering and lighting.
The carpark installation is continuing well at the Tahmoor District Sporting Complex. See the latest image.
The work at the Tahmoor Sporting Complex to realign the sportsgrounds is progressing well. Here are some updates:
Here is the latest update to the Tahmoor Sporting Complex and the realignment of the soccer and cricket fields.
Here is the latest update from Tahmoor Sportsground for the realignment of the cricket and soccer fields.
There is so much happening at the Tahmoor Sportsground for the alignment of the sportsgrounds for soccer and cricket.
✔️ Rainwater reuse tanks for field irrigation are in place
✔️ Cricket pitch has been rolled and under construction
✔️ Sportsfield lighting tower foundations
Earthworks are continuing well at the Tahmoor Sportsground Upgrade - Stage 2 site, with a scraper removing the top layer of soil to be reused in the final stages of the project. The soil will be stockpiled on site until it's required.